PERMIT #6845310-CN

6047 ATLAS PL SW, SEATTLE, WA

new

Permit Timeline & Status

Construction Permit Timeline
Applied
November 14, 2025
In Review
3 cycles
Reviews Done
July 22, 2026
Ready to Issue
July 23, 2026
Issued
Completed
Expires
250
Plan Review Days — Total
68
Plan Review Days — City Control
182
Days in Applicant Control
3
Review Cycles
Next stepPlan review complete — ready to issue, awaiting final fees/issuance.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$25,000
Type
Residential Construction
Issued
N/A
Location
West Seattle

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Construct site improvements to remove portion of development in steep slope and construct gabion walls with piles adjacent to existing one family dwelling per plan.

Additional Details

Permit Intelligence
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0076728
Review cycles
3
Plan review days
250
Days in corrections
182
Units added
0
Units removed
0