PERMIT #6921554-CN
4805 NE 45TH ST, SEATTLE, WA
completedPermit Timeline & Status
Construction Permit Timeline
Applied
November 7, 2024
In Review
—
Issued
March 14, 2025
Completed
March 6, 2026
Expires
September 14, 2026
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$344,646
Type
Commercial Construction
Issued
March 14, 2025
Location
Laurelhurst
Contractor Information
Location & Map
Project Description
4805 NE 45TH ST - Alterations to Establish Daycare Educational Services - St Stephen's Church Establish use as childcare center. Construct alterations in existing institutional building (St. Stephen's Episcopal Church), occupy per plan. Mechanical Included
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
RMILLMI871NH
Review level
Full C
Primary use
Institutional
Parcel
DV0029522
Expires
September 14, 2026
Existing units
0
Sleeping rooms
0