PERMIT #6929343-CN

5453 25TH AVE S, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
April 1, 2025
In Review
Issued
March 30, 2026
Completed
Expires
September 30, 2027
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Other Seattle Neighborhood

Project Overview

Project Details
Value
$623,343
Type
Land
Issued
March 30, 2026
Location
Other Seattle

Contractor Information

Contractor
Owner/Lessee

Location & Map

Project Description
Construction Permit (Establish use as single family dwelling unit, per land use code.) Construct new one family dwelling, per plan.

Additional Details

Permit Intelligence
Work performed by
Owner/Lessee
Review level
Full C
Primary use
Vacant Land
Parcel
DV0069071
Expires
September 30, 2027
Existing units
0
Sleeping rooms
0
Open official SDCI detail →
Open Map