PERMIT #7001915-CN

2506 W HALLADAY ST, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
June 27, 2024
In Review
Issued
February 28, 2025
Completed
November 12, 2025
Expires
August 28, 2026
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$75,000
Type
Residential Construction
Issued
February 28, 2025
Location
Magnolia

Contractor Information

Contractor
CONCRETE DREAMS LLC
General Contractor
License CONCRDL787R8

Location & Map

Project Description
2506 W Halladay St - Construction - Slater project Construct sitework and retaining walls for single-family residence, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
CONCRDL787R8
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0082356
Expires
August 28, 2026
Existing units
1
Sleeping rooms
0
Open official SDCI detail →
View Contractor