PERMIT #7009806-GR
4615 8TH AVE NW, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
October 1, 2024
In Review
—
Issued
July 7, 2025
Completed
—
Expires
January 7, 2027
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
N/A
Type
Land
Issued
July 7, 2025
Location
Fremont
Contractor Information
Location & Map
Project Description
4615 8th Ave NW - Grading - Contaminated soil excavation/remediation Grading to remove contaminated soil, regrade site to original grades, and re-pave site, per plan. PASV and reviews under permit record #6971594-GR.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
INNOVCS781K5
Review level
Full +
Primary use
Vacant Land
Parcel
DV0056514
Expires
January 7, 2027