PERMIT #7010706-CN
718 N 76TH ST, SEATTLE, WA
completedPermit Timeline & Status
Construction Permit Timeline
Applied
June 5, 2024
In Review
—
Issued
November 18, 2024
Completed
September 24, 2025
Expires
May 18, 2026
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
718 N 76TH ST, SEATTLE, WA Property
Addition at 718 N 76TH ST Project
JSM CONSTRUCTION INC Contractor
Green Lake Neighborhood
Project Overview
Project Details
Value
$98,570
Type
Residential Construction
Issued
November 18, 2024
Location
Green Lake
Contractor Information
Location & Map
Project Description
Glassburn Addition Allow detached accessory dwelling unit per Land Use Code. Construct 2nd story addition and substantial alterations to existing garage and convert to a one-family dwelling, per plans.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
JSMCOCI772BK
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0056491
Expires
May 18, 2026
Existing units
0
Sleeping rooms
0