PERMIT #7013102-CN

1111 N 76TH ST, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
July 25, 2024
In Review
Issued
April 15, 2025
Completed
March 26, 2026
Expires
October 15, 2026
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Green Lake Neighborhood

Project Overview

Project Details
Value
$566,619
Type
Residential Construction
Issued
April 15, 2025
Location
Green Lake

Contractor Information

Contractor
UPPER LEFT LIVING LLC
General Contractor
License UPPERLL806R3

Location & Map

Project Description
SFR+2AADU Allow two attached accessory dwelling units with an existing single-family residence per land use code. Construct addition & substantial alterations to a one-family dwelling for a townhouse building, per plan

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
UPPERLL806R3
Review level
Full C
Primary use
Single Family/Duplex
Parcel
DV1168160
Expires
October 15, 2026
Existing units
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor