PERMIT #7017972-CN
601 UNION ST, SEATTLE, WA
completedPermit Timeline & Status
Construction Permit Timeline
Applied
December 10, 2024
In Review
—
Issued
January 30, 2025
Completed
September 30, 2025
Expires
July 30, 2026
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$6,000
Type
Commercial Construction
Issued
January 30, 2025
Location
Downtown
Contractor Information
Contractor
Owner/Lessee
Location & Map
Project Description
TUS - 40 & 41 Construct alterations to existing office building at levels 40 and 41, per plan.
Additional Details
Permit Intelligence
Work performed by
Owner/Lessee
Review level
Full +
Primary use
Commercial
Parcel
DV0010156
Expires
July 30, 2026
Existing units
0
Sleeping rooms
0