PERMIT #7022267-CN

2357 29TH AVE S, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
May 15, 2024
In Review
Issued
June 17, 2024
Completed
April 24, 2025
Expires
December 17, 2025
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Beacon Hill Neighborhood

Project Overview

Project Details
Value
$15,000
Type
Residential Construction
Issued
June 17, 2024
Location
Beacon Hill

Contractor Information

Contractor
Owner/Lessee

Location & Map

Project Description
ROLLOLAZO ADU Allow attached accessory dwelling unit (AADU) to existing residence, per land use code. Construct alterations for additional dwelling unit in finished basement of existing one-family dwelling, per plan.

Additional Details

Permit Intelligence
Work performed by
Owner/Lessee
Review level
Full
Primary use
Single Family/Duplex
Parcel
DV1193891
Expires
December 17, 2025
Existing units
0
Sleeping rooms
0
Open official SDCI detail →
Open Map