PERMIT #7024315-CN
2019 BOREN AVE, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
September 23, 2024
In Review
—
Issued
August 22, 2025
Completed
—
Expires
February 22, 2027
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
2019 BOREN AVE, SEATTLE, WA Property
Renovation at 2019 BOREN AVE Project
HOLLAND CONSTRUCTION INC Contractor
Downtown Neighborhood
Project Overview
Project Details
Value
$10,577,870
Type
Commercial Construction
Issued
August 22, 2025
Location
Downtown
Contractor Information
Location & Map
Project Description
Office to Residential Tower Conversion Change of use from office use to apartment (multifamily residential), per land use code. Construct alterations to convert office space to apartments at floors 2, 3, 4, and 1 (NW lobby) of existing high-rise mixed-use building, occupy per plan
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
HOLLACI952DJ
Review level
Full C
Primary use
Commercial
Parcel
DV0094301
Expires
February 22, 2027
Existing units
406
Sleeping rooms
0