PERMIT #7024953-CN

5427 31ST AVE SW, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
June 26, 2024
In Review
Issued
May 22, 2025
Completed
January 6, 2026
Expires
November 22, 2026
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$85,000
Type
Residential Construction
Issued
May 22, 2025
Location
West Seattle

Contractor Information

Contractor
CADRE GENERAL CONTRACTORS LLC
General Contractor
License CADREGC806MH

Location & Map

Project Description
Kozak Basement Remodel Construct additions and alterations to existing one-family dwelling, per plan

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
CADREGC806MH
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1143250
Expires
November 22, 2026
Existing units
1
Sleeping rooms
0
Open official SDCI detail →
View Contractor