PERMIT #7025584-CN
1451 23RD AVE W, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
September 9, 2024
In Review
—
Issued
June 24, 2025
Completed
—
Expires
December 24, 2026
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$3,800,000
Type
Commercial Construction
Issued
June 24, 2025
Location
Magnolia
Contractor Information
Contractor
Not published by SDCI
Location & Map
Project Description
Smith Cove Park Development Construct alterations and grading to develop Smith Cove Park athletic fields, fenced off-leash area, bio-retention area, planting and accessible paths and steps, per plan.
Additional Details
Permit Intelligence
Work performed by
Authorized Government Representative
Review level
Full C
Primary use
Institutional
Parcel
DV0340998
Expires
December 24, 2026
Existing units
0
Sleeping rooms
0