PERMIT #7026195-CN
2311 N 55TH ST, SEATTLE, WA
completedPermit Timeline & Status
Construction Permit Timeline
Applied
July 19, 2024
In Review
—
Issued
September 12, 2024
Completed
April 11, 2025
Expires
March 12, 2026
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Green Lake Neighborhood
Project Overview
Project Details
Value
$283,016
Type
Residential Construction
Issued
September 12, 2024
Location
Green Lake
Contractor Information
Contractor
Owner/Lessee
Location & Map
Project Description
Construction Permit Construct addition and substantial alteration to existing one family dwelling, existing foundation and floor framing to remain, per plan.
Additional Details
Permit Intelligence
Work performed by
Owner/Lessee
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1137936
Expires
March 12, 2026
Existing units
0
Sleeping rooms
0