PERMIT #7026935-CN

400 QUEEN ANNE AVE N, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
July 2, 2024
In Review
Issued
December 9, 2024
Completed
March 12, 2025
Expires
June 9, 2026
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$1,040,957
Type
Residential Construction
Issued
December 9, 2024
Location
Other Seattle

Contractor Information

Contractor
HST CONSTRUCTION INC
General Contractor
License HSTCOCI920KA

Location & Map

Project Description
MVMT MTHD [Change use from general retail sales and service to indoor sports and recreation per land use code.] Construct initial tenant improvement in a mixed-use building on first floor, occupy per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
HSTCOCI920KA
Review level
Full +
Primary use
Multifamily
Parcel
DV0337418
Expires
June 9, 2026
Existing units
0
Sleeping rooms
0
Open official SDCI detail →