PERMIT #7027961-CN

9253 18TH AVE SW, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
September 15, 2025
In Review
2 cycles
Reviews Done
November 13, 2025
Ready to Issue
November 22, 2025
Issued
November 24, 2025
Completed
Expires
May 24, 2027
59
Plan Review Days — Total
24
Plan Review Days — City Control
35
Days in Applicant Control
2
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$253,014
Type
Residential Construction
Issued
November 24, 2025
Location
White Center

Contractor Information

Contractor
PACIFIC NORTHWEST RSTRTN1 LLC
General Contractor
License PACIFNR784JD

Location & Map

Project Description
9253 18th Ave SW - Ext'g SFR Sub Alt - Phanivong Project Construct substantial alterations to single family dwelling, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
PACIFNR784JD
Housing category
Single-Family Add/Alt
Review level
Full
Primary use
Single Family/Duplex
Parcel
DV0017913
Review cycles
2
Plan review days
59
Days in corrections
35
Expires
May 24, 2027
Existing units
1
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor