Construction Permit Timeline
Applied
June 6, 2024
In Review
Issued
July 24, 2024
Completed
April 4, 2025
Expires
January 24, 2026
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Ballard Neighborhood

Project Overview

Project Details
Value
$173,950
Type
Residential Construction
Issued
July 24, 2024
Location
Ballard

Contractor Information

Contractor
SHEPHERD PROPERTIES PNW LLC
General Contractor
License SHEPHPP761K4

Location & Map

Project Description
Hundtoft DADU Construct detached accessory dwelling unit (DADU) accessory to single family residence per standard plan 6794017-SP. (Construct new one-family detached accessory dwelling unit and alterations to existing one family dwelling under the building code, per plans. Process both records under 7029267-CN.)

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
SHEPHPP761K4
Review level
Full
Primary use
Single Family/Duplex
Parcel
DV1148832
Expires
January 24, 2026
Existing units
0
Sleeping rooms
0