PERMIT #7036337-CN
500 9TH AVE N, SEATTLE, WA
completedPermit Timeline & Status
Construction Permit Timeline
Applied
July 19, 2024
In Review
—
Issued
July 19, 2024
Completed
December 2, 2024
Expires
January 19, 2026
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
CORTI CONSTRUCTION INC Contractor
South Lake Union Neighborhood
Project Overview
Project Details
Value
$283,000
Type
Commercial Construction
Issued
July 19, 2024
Location
South Lake Union
Contractor Information
Location & Map
Project Description
39JW012407 Construct alterations to Business Service Center, Level 01 (Splice) of existing commercial building, subject to field inspection (STFI)
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
CORTICI838JO
Review level
Field
Primary use
Commercial
Parcel
DV0079356
Expires
January 19, 2026