PERMIT #7041366-CN
1610 BELMONT AVE, Seattle, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
November 12, 2025
In Review
2 cycles
Reviews Done
April 10, 2026
Ready to Issue
April 20, 2026
Issued
June 15, 2026
Completed
—
Expires
—
149
Plan Review Days — Total
32
Plan Review Days — City Control
117
Days in Applicant Control
2
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
1610 BELMONT AVE, Seattle, WA Property
Renovation at 1610 BELMONT AVE Project
Capitol Hill Neighborhood
Project Overview
Project Details
Value
$1,903,049
Type
Residential Construction
Issued
June 15, 2026
Location
Capitol Hill
Contractor Information
Contractor
Not published by SDCI
Location & Map
Project Description
Construct exterior alterations/repairs to multifamily building (South Building 1) per plan.
Additional Details
Permit Intelligence
Review level
Full +
Primary use
Multifamily
Parcel
DV0056901
Review cycles
2
Plan review days
149
Days in corrections
117
Units added
0
Units removed
0