PERMIT #7041426-CN
5945 39TH AVE S, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
September 6, 2024
In Review
—
Issued
June 20, 2025
Completed
—
Expires
December 20, 2026
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$3,427,771
Type
Commercial Construction
Issued
June 20, 2025
Location
Hillman City
Contractor Information
Location & Map
Project Description
CHAM community center Establish use as community center, per land use code. Construct new Community Building (CHAM Community Center), occupy per plan. Mechanical included
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
ZSAINI*846CW
Review level
Full C
Primary use
Institutional
Parcel
DV0339461
Expires
December 20, 2026
Existing units
0
Sleeping rooms
0