activePermit Timeline & Status
Construction Permit Timeline
Applied
December 1, 2025
In Review
3 cycles
Reviews Done
March 31, 2026
Ready to Issue
March 31, 2026
Issued
April 1, 2026
Completed
—
Expires
October 1, 2027
120
Plan Review Days — Total
62
Plan Review Days — City Control
58
Days in Applicant Control
3
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
4229 AIKINS AVE SW, SEATTLE, WA Property
West Seattle Neighborhood
Project Overview
Project Details
Value
$10,000
Type
Residential Construction
Issued
April 1, 2026
Location
West Seattle
Contractor Information
Contractor
Owner/Lessee
Location & Map
Project Description
West Wall Removal Construct site improvements adjacent to one-family dwelling, per plan.
Additional Details
Permit Intelligence
Work performed by
Owner/Lessee
Housing category
Single-Family Add/Alt
Review level
Full
Primary use
Single Family/Duplex
Parcel
DV0067777
Review cycles
3
Plan review days
120
Days in corrections
58
Expires
October 1, 2027
Existing units
1
Units added
0
Units removed
0
Sleeping rooms
0