Construction Permit Timeline
Applied
November 7, 2024
In Review
—
Issued
January 29, 2025
Completed
—
Expires
July 29, 2026
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
3807 WALLA WALLA RD NE, SEATTLE, WA Property
CENTENNIAL CONTRACTORS ENT INC Contractor
University District Neighborhood
Project Overview
Project Details
Value
$200,000
Type
Commercial Construction
Issued
January 29, 2025
Location
University District
Contractor Information
Location & Map
Project Description
Construction Permit Construct alterations to UW Softball Field, per plan
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
CENTECE004KK
Review level
Full +
Primary use
Institutional
Parcel
DV0015299
Expires
July 29, 2026
Existing units
0
Sleeping rooms
0