PERMIT #7044378-CN
2320 43RD AVE E, SEATTLE, WA
completedPermit Timeline & Status
Construction Permit Timeline
Applied
September 5, 2024
In Review
—
Issued
September 9, 2024
Completed
June 4, 2025
Expires
March 9, 2026
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
THOMAS JACOBSON CONST INC Contractor
Madison Park Neighborhood
Project Overview
Project Details
Value
$15,000
Type
Residential Construction
Issued
September 9, 2024
Location
Madison Park
Contractor Information
Location & Map
Project Description
LAZZARA CONDO Construct interior alteration to existing condo unit #305A, per STFI
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
THOMAJC926CM
Review level
Field
Primary use
Multifamily
Parcel
DV0074664
Expires
March 9, 2026