PERMIT #7045032-CN

1100 DEXTER AVE N, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
September 9, 2024
In Review
Issued
September 10, 2024
Completed
October 8, 2024
Expires
March 10, 2026
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
South Lake Union Neighborhood

Project Overview

Project Details
Value
$7,500
Type
Commercial Construction
Issued
September 10, 2024
Location
South Lake Union

Contractor Information

Contractor
D P INC GENERAL CONTRACTORS
General Contractor
License DPINCGC066BU

Location & Map

Project Description
PNNL Room 544 Tenant improvements to existing office on level 5 of existing office building (Pacific NW Nat. Laboratory - Bldg 2), subject to field inspection, STFI.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
DPINCGC066BU
Review level
Field
Primary use
Commercial
Parcel
DV0066509
Expires
March 10, 2026
Open official SDCI detail →