PERMIT #7046509-CN
1050 SW Spokane St, Seattle, WA
Active1050 SW Spokane St - Construction and Grading - Terminal 18 Shore Power Construct north substation and associated power vault and sitework, per plan. [Construct shore power vaults, substations, and associated site… at 1050 SW Spokane St, Seattle, WA in West Seattle, Seattle. Permit 7046509-CN is active, valued at $11,009,334. Work is being performed by SHIMMICK CONSTRUCTION CO INC.
Permit Timeline & Status
Construction Permit Timeline
AppliedJune 17, 2025
In Review—
IssuedMarch 6, 2026
Completed—
ExpiresSeptember 6, 2027
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
1050 SW SPOKANE ST, SEATTLE, WA Property
Renovation at 1050 SW SPOKANE ST Project
SHIMMICK CONSTRUCTION CO INC Contractor
West Seattle Neighborhood
Project Overview
Project Details
- Value
- $11,009,334
- Type
- Industrial Construction
- Issued
- March 6, 2026
- Location
- West Seattle
Contractor Information
Location & Map
Development site
DV0066407
- Site area
- 5,437,857 sq ft
- Site status
- ACTIVE
- Source updated
- Dec 7, 2017
- Last checked
- Nov 28, 2026
Current SDCI site context. The outline shows the development-site boundary used for code standards.
Official Seattle development-site data →Project Description
1050 SW Spokane St - Construction and Grading - Terminal 18 Shore Power Construct north substation and associated power vault and sitework, per plan. [Construct shore power vaults, substations, and associated site alterations for container terminal [PORT OF SEATTLE, TERMINAL 18], per plan. Review and processing for (3) construction records under 7046509-CN.]
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
SHIMMCC905JB
Review level
Full C
Primary use
Industrial
Property reference
DV0066407
Expires
September 6, 2027
Existing units
0
Sleeping rooms
0