PERMIT #7046512-CN
807 NE 71ST ST, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
January 30, 2025
In Review
—
Issued
August 26, 2025
Completed
—
Expires
February 26, 2027
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
807 NE 71ST ST, SEATTLE, WA Property
Roosevelt Neighborhood
Project Overview
Project Details
Value
$1,261,013
Type
Residential Construction
Issued
August 26, 2025
Location
Roosevelt
Contractor Information
Contractor
Owner/Lessee
Location & Map
Project Description
7018 8TH AVE NE - TH & Duplex (North TH) Construct new North townhouse per plan. Construct new townhouse and two family dwellings, per plan. (Review and processing for two records under 7046512-CN). PROJECT IS SUBJECT TO THE SIP LIT PILOT PROGRAM
Additional Details
Permit Intelligence
Work performed by
Owner/Lessee
Review level
Full C
Primary use
Multifamily
Parcel
DV0360180
Expires
February 26, 2027
Existing units
0
Sleeping rooms
0