Permit Timeline & Status

Construction Permit Timeline
Applied
September 19, 2024
In Review
Issued
September 23, 2024
Completed
November 1, 2024
Expires
March 23, 2026
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Georgetown Neighborhood

Project Overview

Project Details
Value
$380
Type
Residential Construction
Issued
September 23, 2024
Location
Georgetown

Contractor Information

Contractor
Owner/Lessee

Location & Map

Project Description
Garage "Complete and final for 6108713-CN" "Complete and final for 6108713-CN" Garage

Additional Details

Permit Intelligence
Work performed by
Owner/Lessee
Review level
Field
Primary use
Multifamily
Parcel
DV0072675
Expires
March 23, 2026