PERMIT #7047059-CN
515 WESTLAKE AVE N, SEATTLE, WA
completedPermit Timeline & Status
Construction Permit Timeline
Applied
September 19, 2024
In Review
—
Issued
September 24, 2024
Completed
February 4, 2025
Expires
March 24, 2026
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
South Lake Union Neighborhood
Project Overview
Project Details
Value
$2,000
Type
Commercial Construction
Issued
September 24, 2024
Location
South Lake Union
Contractor Information
Contractor
Owner/Lessee
Location & Map
Project Description
38SL042409 Install pre-manufactured floor to ceiling partitions in existing commercial tenant space L4, subject to field inspection (STFI)
Additional Details
Permit Intelligence
Work performed by
Owner/Lessee
Review level
Field
Primary use
Commercial
Parcel
DV0079356
Expires
March 24, 2026