PERMIT #7047884-CN
7904 20TH AVE SW, SEATTLE, WA
completedPermit Timeline & Status
Construction Permit Timeline
Applied
October 24, 2024
In Review
—
Issued
February 5, 2025
Completed
September 25, 2025
Expires
August 5, 2026
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$215,825
Type
Residential Construction
Issued
February 5, 2025
Location
West Seattle
Contractor Information
Location & Map
Project Description
Garbowitz DADU Allow new detached accessory dwelling unit to existing single family use per land use code. Construct new one family dwelling, remove detached accessory garage, per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
BACKYAL786JM
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1095868
Expires
August 5, 2026
Existing units
0
Sleeping rooms
2