completedRyther Central Mechanical Systems Construct non-structural alterations to existing commercial building Ryther Central Building, subject-to-field inspection (STFI) at 2400 NE 95th St, Seattle, WA in Maple Leaf, Seattle. Permit 7049849-CN is completed, valued at $10,000. Work is being performed by PENNON CONSTRUCTION CO INC.
Permit Timeline & Status
Construction Permit Timeline
Applied
October 28, 2024
In Review
—
Issued
October 29, 2024
Completed
May 1, 2025
Expires
April 29, 2026
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$10,000
Type
Commercial Construction
Issued
October 29, 2024
Location
Maple Leaf
Contractor Information
Location & Map
Project Description
Ryther Central Mechanical Systems Construct non-structural alterations to existing commercial building Ryther Central Building, subject-to-field inspection (STFI)
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
PENNOCC013Q3
Review level
Field
Primary use
Institutional