PERMIT #7050158-CN

119 HARVARD AVE E, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
October 30, 2024
In Review
Issued
November 19, 2024
Completed
January 8, 2025
Expires
May 19, 2026
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Capitol Hill Neighborhood

Project Overview

Project Details
Value
$8,390
Type
Residential Construction
Issued
November 19, 2024
Location
Capitol Hill

Contractor Information

Contractor
BETACOM INCORPORATED
General Contractor
License BETACI*828MR

Location & Map

Project Description
SE52XC156 Ramayana Sprint Decom Construct alterations to decommission minor telecommunications facility (T-Mobile for Sprint/Clearwire ) on rooftop of existing multifamily building, per plan

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
BETACI*828MR
Review level
Full +
Primary use
Multifamily
Parcel
DV0067997
Expires
May 19, 2026
Existing units
0
Sleeping rooms
0