PERMIT #7051518-CN

425 BROADWAY E, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
October 30, 2024
In Review
Issued
December 9, 2024
Completed
Expires
June 9, 2026
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Capitol Hill Neighborhood

Project Overview

Project Details
Value
$25,000
Type
Commercial Construction
Issued
December 9, 2024
Location
Capitol Hill

Contractor Information

Contractor
Not published by SDCI
License MASTENS863JS

Location & Map

Project Description
SC79 NORTH CAPITOL HILL 10097991 LTE 1C RRH SWAP Construct alterations to minor telecommunications facility (AT&T) at the roof level of retail building, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
MASTENS863JS
Review level
Full +
Primary use
Commercial
Parcel
DV0008139
Expires
June 9, 2026
Existing units
0
Sleeping rooms
0