PERMIT #7053245-CN

6030 51ST PL S, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
August 23, 2025
In Review
3 cycles
Issued
May 6, 2026
Completed
Expires
November 6, 2027
254
Plan Review Days — Total
41
Plan Review Days — City Control
213
Days in Applicant Control
3
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
HAUS MAUS LLC Contractor
Seward Park Neighborhood

Project Overview

Project Details
Value
$327,470
Type
Residential Construction
Issued
May 6, 2026
Location
Seward Park

Contractor Information

Contractor
HAUS MAUS LLC
General Contractor
License HAUSMML772NN

Location & Map

Project Description
Schwartz - Addition Construct addition and substantial alterations to existing single-family dwelling, per plans.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
HAUSMML772NN
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1177209
Review cycles
3
Plan review days
254
Days in corrections
213
Expires
November 6, 2027
Existing units
1
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →