PERMIT #7057273-CN

2125 1ST AVE, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
November 19, 2024
In Review
Issued
March 17, 2025
Completed
April 29, 2026
Expires
September 17, 2026
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Belltown Neighborhood

Project Overview

Project Details
Value
$1,100,000
Type
Residential Construction
Issued
March 17, 2025
Location
Belltown

Contractor Information

Contractor
LOCKHART-SUVER LLC
General Contractor
License LOCKHL*962O8

Location & Map

Project Description
Continental Place STFI Construct interior alterations to unit #3302 in existing multi-family building, per STFI.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
LOCKHL*962O8
Review level
Field
Primary use
Multifamily
Parcel
DV0074844
Expires
September 17, 2026
Existing units
1
Sleeping rooms
2
Open official SDCI detail →