PERMIT #7059318-CN

11504 RIVIERA PL NE, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
October 29, 2025
In Review
1 cycle
Reviews Done
November 17, 2025
Ready to Issue
November 19, 2025
Issued
November 19, 2025
Completed
March 13, 2026
Expires
May 19, 2027
19
Plan Review Days — Total
19
Plan Review Days — City Control
0
Days in Applicant Control
1
Review Cycles
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$47,300
Type
Residential Construction
Issued
November 19, 2025
Location
Lake City

Contractor Information

Contractor
WATERS & WOOD INCORPORATED
General Contractor
License WATERWI088RM

Location & Map

Project Description
Rekhi pier repair Construct repairs to existing dock piers, remove stairway at shoreline, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
WATERWI088RM
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0010970
Review cycles
1
Plan review days
19
Days in corrections
0
Expires
May 19, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →