Permit Timeline & Status

Construction Permit Timeline
Applied
January 2, 2025
In Review
Issued
March 17, 2025
Completed
Expires
September 17, 2026
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$75,000
Type
Commercial Construction
Issued
March 17, 2025
Location
First Hill

Contractor Information

Contractor
Owner/Lessee

Location & Map

Project Description
Bridget - Sue Genty Interior Design Inc Tenant improvement to existing commercial building at L1 for catering kitchen, per plan.

Additional Details

Permit Intelligence
Work performed by
Owner/Lessee
Review level
Full +
Primary use
Commercial
Parcel
DV0057228
Expires
September 17, 2026
Existing units
0
Sleeping rooms
0
Open official SDCI detail →
Open Map