PERMIT #7061478-CN

325 9th Ave, Seattle, WA

Completed

Construction Permit Construct tenant improvements to existing Hospital (Harbor View Medical Center) on Level 1 and G, per plan. Mechanical Included at 325 9th Ave, Seattle, WA in First Hill, Seattle. Permit 7061478-CN is completed, valued at $1,000,000. Work is being performed by G L Y CONSTRUCTION INC.

Permit Timeline & Status

Construction Permit Timeline
AppliedJanuary 28, 2025
In Review—
IssuedMarch 24, 2025
CompletedDecember 2, 2025
ExpiresSeptember 24, 2026
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
First Hill Neighborhood

Project Overview

Project Details
Value
$1,000,000
Type
Commercial Construction
Issued
March 24, 2025
Location
First Hill

Contractor Information

Contractor
G L Y CONSTRUCTION INC
General Contractor
License GLYCOI*018O9

Location & Map

Development site
DV0065890
Site area
163,938 sq ft
Site status
ACTIVE
Source updated
Jul 17, 2018
Last checked
Nov 28, 2026

Current SDCI site context. The outline shows the development-site boundary used for code standards.

Official Seattle development-site data →
Project Description
Construction Permit Construct tenant improvements to existing Hospital (Harbor View Medical Center) on Level 1 and G, per plan. Mechanical Included.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
GLYCOI*018O9
Review level
Full +
Primary use
Institutional
Property reference
DV0065890
Expires
September 24, 2026
Existing units
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor