PERMIT #7061646-CN

2219 SW ANDOVER ST, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
December 29, 2025
In Review
3 cycles
Reviews Done
April 24, 2026
Ready to Issue
April 28, 2026
Issued
April 28, 2026
Completed
May 15, 2026
Expires
October 28, 2027
116
Plan Review Days — Total
49
Plan Review Days — City Control
67
Days in Applicant Control
3
Review Cycles
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$65,000
Type
Residential Construction
Issued
April 28, 2026
Location
West Seattle

Contractor Information

Contractor
PACIFIC NW SIDING/WINDOWS INC
General Contractor
License PACIFNS991BT

Location & Map

Project Description
Robert Hendershott Construct alterations to existing two family dwelling, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
PACIFNS991BT
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0001284
Review cycles
3
Plan review days
116
Days in corrections
67
Expires
October 28, 2027
Existing units
2
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →