PERMIT #7062051-CN
405 15TH AVE E, SEATTLE, WA
completedPermit Timeline & Status
Construction Permit Timeline
Applied
January 13, 2025
In Review
—
Issued
February 10, 2025
Completed
March 18, 2025
Expires
August 10, 2026
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$8,390
Type
Commercial Construction
Issued
February 10, 2025
Location
Capitol Hill
Contractor Information
Location & Map
Project Description
405 15th Ave E - Equipment Removal - T-Mobile SE73XC047 Sprint Decom Remove minor telecommunications equipment [T-MOBILE/SPRINT] at roof level of commercial building [RETAIL STORES], per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
BETACI*828MR
Review level
Full
Primary use
Commercial
Parcel
DV0019681
Expires
August 10, 2026
Existing units
0
Sleeping rooms
0