PERMIT #7064962-CN
11414 9TH AVE NW, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
November 12, 2025
In Review
3 cycles
Reviews Done
July 23, 2026
Ready to Issue
July 24, 2026
Issued
July 24, 2026
Completed
—
Expires
—
253
Plan Review Days — Total
67
Plan Review Days — City Control
186
Days in Applicant Control
3
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$250,000
Type
Residential Construction
Issued
July 24, 2026
Location
Broadview
Contractor Information
Contractor
Not published by SDCI
Location & Map
Project Description
Construct alterations to existing one family dwelling per plan.
Additional Details
Permit Intelligence
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1103667
Review cycles
3
Plan review days
253
Days in corrections
186
Units added
0
Units removed
0