PERMIT #7065639-CN
100 4TH AVE N, SEATTLE, WA
completedPermit Timeline & Status
Construction Permit Timeline
Applied
February 21, 2025
In Review
—
Issued
June 23, 2025
Completed
February 26, 2026
Expires
December 23, 2026
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$1,000,000
Type
Commercial Construction
Issued
June 23, 2025
Location
Belltown
Contractor Information
Location & Map
Project Description
Verizon Cooling and Ventilation Systems Upgrades Remove and replace mechanical equipment on second floor and roof of commercial building, per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
TISHMCC831K4
Review level
Full C
Primary use
Commercial
Parcel
DV0027811
Expires
December 23, 2026
Existing units
0
Sleeping rooms
0