PERMIT #7068740-CN

402 Cedar ST, Seattle, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
April 12, 2025
In Review
Issued
April 30, 2025
Completed
Expires
October 30, 2026
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Pro-Mondo LLC Contractor
Belltown Neighborhood

Project Overview

Project Details
Value
$6,000
Type
Commercial Construction
Issued
April 30, 2025
Location
Belltown

Contractor Information

Contractor
Pro-Mondo LLC
General Contractor
License PROMOL*883MU

Location & Map

Project Description
402 Cedar St demising wall Construct demising wall in existing mixed-use building, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
PROMOL*883MU
Review level
Full +
Primary use
Commercial
Parcel
DV0027852
Expires
October 30, 2026
Existing units
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor