PERMIT #7073602-CN

8100 2nd Ave S, Seattle, WA

New

Seattle South Transfer Station Phase 2 Construct new office building (Crew Quarters building), Transformer pad, retaining walls, fencing and site improvements, occupy per plan. (Construct 1 office, 1 transfer trailer… at 8100 2nd Ave S, Seattle, WA in South Park, Seattle. Permit 7073602-CN is new, valued at $347,725.

Permit Timeline & Status

Construction Permit Timeline
AppliedApril 14, 2025
In ReviewIn progress
Issued—
Completed—
Expires—
Next stepIn City review — awaiting the next action.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
South Park Neighborhood

Project Overview

Project Details
Value
$347,725
Type
Industrial Construction
Issued
N/A
Location
South Park

Contractor Information

Contractor
Not published by SDCI

Location & Map

Development site
DV0075857
Site area
454,929 sq ft
Site status
ACTIVE
Source updated
Aug 6, 2009
Last checked
Nov 28, 2026

Current SDCI site context. The outline shows the development-site boundary used for code standards.

Official Seattle development-site data →
Project Description
Seattle South Transfer Station Phase 2 Construct new office building (Crew Quarters building), Transformer pad, retaining walls, fencing and site improvements, occupy per plan. (Construct 1 office, 1 transfer trailer canopy, 1 commercial building (Elec/ IT building), 1 pump station with water quality treatment facility and associated site improvements. Review and processing of 4 records under 7073602-CN)

Additional Details

Permit Intelligence
Work performed by
Public Utility
Review level
Full C
Primary use
Industrial
Property reference
DV0075857
Existing units
0
Sleeping rooms
0