PERMIT #7074022-CN
8755 13TH AVE NW, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
October 15, 2025
In Review
5 cycles
Reviews Done
June 2, 2026
Ready to Issue
June 2, 2026
Issued
June 22, 2026
Completed
—
Expires
—
230
Plan Review Days — Total
66
Plan Review Days — City Control
164
Days in Applicant Control
5
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
8755 13TH AVE NW, SEATTLE, WA Property
Crown Hill Neighborhood
Project Overview
Project Details
Value
$235,014
Type
Residential Construction
Issued
June 22, 2026
Location
Crown Hill
Contractor Information
Contractor
Not published by SDCI
Location & Map
Project Description
Construct NW one-family dwelling [Unit 1] (Establish use as townhouses and single-family dwelling units per land use code. Construct (4) one-family dwellings per plan. Review & process for (4) records under 7074022-CN)
Additional Details
Permit Intelligence
Review level
Full C
Primary use
Single Family/Duplex
Parcel
DV0048099
Review cycles
5
Plan review days
230
Days in corrections
164
Units added
1
Units removed
0