PERMIT #7075635-CN

14312 30TH AVE NE, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
March 16, 2025
In Review
Issued
November 12, 2025
Completed
Expires
May 12, 2027
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$1,423,484
Type
Residential Construction
Issued
November 12, 2025
Location
Pinehurst

Contractor Information

Contractor
VENTURE GENERAL CONTRCTNG LLC
General Contractor
License VENTUGC899LZ

Location & Map

Project Description
Seattle Housing Authority Jackson Park Apartments - West Bldg C Construct west townhouse building C, occupy per plan. Mechanical is included. (Establish use as apartment and townhouses per land use code. Construct one multi-family building with below grade parking and three townhouse buildings. Review and processing for 4 records under #6757668-CN)

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
VENTUGC899LZ
Review level
Dependent Building
Primary use
Multifamily
Parcel
DV0040958
Expires
May 12, 2027
Existing units
0
Sleeping rooms
0
Open official SDCI detail →