PERMIT #7075832-CN

400 WESTLAKE AVE N, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
June 26, 2025
In Review
Issued
October 28, 2025
Completed
Expires
April 28, 2027
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$1,141,875
Type
Commercial Construction
Issued
October 28, 2025
Location
South Lake Union

Contractor Information

Contractor
SKYLINE CONSTRUCTION
Commercial
License SKYLIC*773DW

Location & Map

Project Description
Charles Schwab Office Establish use as Office per land use code. Construct tenant improvements to portions of L-1 & L-12 in a commercial high-rise building, occupy per plan. Mechanical included this permit

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
SKYLIC*773DW
Review level
Full +
Primary use
Commercial
Parcel
DV0041502
Expires
April 28, 2027
Existing units
0
Sleeping rooms
0
Open official SDCI detail →