PERMIT #7077275-DM

14338 30TH AVE NE, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
September 3, 2025
In Review
3 cycles
Issued
December 4, 2025
Completed
March 3, 2026
Expires
June 4, 2027
79
Plan Review Days — Total
37
Plan Review Days — City Control
42
Days in Applicant Control
3
Review Cycles
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$50,000,000
Type
Residential Construction
Issued
December 4, 2025
Location
Pinehurst

Contractor Information

Contractor
VENTURE GENERAL CONTRCTNG LLC
General Contractor
License VENTUGC899LZ

Location & Map

Project Description
Seattle Housing Authority Jackson Park Apartments Demolish existing multifamily building (Building I), per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
VENTUGC899LZ
Review level
Full +
Primary use
Multifamily
Parcel
DV0040958
Review cycles
3
Plan review days
79
Days in corrections
42
Expires
June 4, 2027
Existing units
5
Units added
0
Units removed
5
Sleeping rooms
0
Open official SDCI detail →
View Contractor