PERMIT #7077409-CN
7011 42ND AVE NE, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
September 25, 2025
In Review
3 cycles
Reviews Done
December 12, 2025
Ready to Issue
December 15, 2025
Issued
December 15, 2025
Completed
—
Expires
June 15, 2027
78
Plan Review Days — Total
32
Plan Review Days — City Control
46
Days in Applicant Control
3
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
7011 42ND AVE NE, SEATTLE, WA Property
Addition at 7011 42ND AVE NE Project
VALOR BUILDS COLLABORATIVE LLC Contractor
Ravenna Neighborhood
Project Overview
Project Details
Value
$491,453
Type
Residential Construction
Issued
December 15, 2025
Location
Ravenna
Contractor Information
Location & Map
Project Description
Coleman Residence Construct addition and substantial alterations to existing one-family dwelling, per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
VALORBC846DT
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1184972
Review cycles
3
Plan review days
78
Days in corrections
46
Expires
June 15, 2027
Existing units
1
Units added
0
Units removed
0
Sleeping rooms
0