PERMIT #7077746-CN
3014 C 12TH AVE S, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
September 17, 2025
In Review
5 cycles
Reviews Done
February 27, 2026
Ready to Issue
March 4, 2026
Issued
March 5, 2026
Completed
—
Expires
September 5, 2027
163
Plan Review Days — Total
212
Days in Applicant Control
5
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$507,966
Type
Residential Construction
Issued
March 5, 2026
Location
Other Seattle
Contractor Information
Location & Map
Project Description
Construction Permit Establish use as apartment per land use code. Construct a new two-family dwelling, per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
HYBRIAL902KR
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0089918
Review cycles
5
Plan review days
163
Days in corrections
212
Expires
September 5, 2027
Existing units
0
Units added
2
Units removed
0
Sleeping rooms
0