PERMIT #7078447-CN

305 HARRISON ST, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
September 25, 2025
In Review
3 cycles
Reviews Done
December 17, 2025
Ready to Issue
December 17, 2025
Issued
December 17, 2025
Completed
June 18, 2026
Expires
June 17, 2027
83
Plan Review Days — Total
31
Plan Review Days — City Control
52
Days in Applicant Control
3
Review Cycles
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$70,000
Type
Commercial Construction
Issued
December 17, 2025
Location
Belltown

Contractor Information

Contractor
STERLING Telecom & Const Inc
General Contractor
License STERLTC884C9

Location & Map

Project Description
Verizon EXPO DAS Node 8 Construct new light pole with minor telecommunication antenna facility (Verizon), per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
STERLTC884C9
Housing category
Commercial Add/Alt
Review level
Full +
Primary use
Commercial
Parcel
DV1199717
Review cycles
3
Plan review days
83
Days in corrections
52
Expires
June 17, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor