PERMIT #7078659-CN
321 MERCER ST, SEATTLE, WA
completedPermit Timeline & Status
Construction Permit Timeline
Applied
September 11, 2025
In Review
3 cycles
Reviews Done
December 17, 2025
Ready to Issue
December 17, 2025
Issued
December 17, 2025
Completed
June 18, 2026
Expires
June 17, 2027
97
Plan Review Days — Total
18
Plan Review Days — City Control
79
Days in Applicant Control
3
Review Cycles
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
321 MERCER ST, SEATTLE, WA Property
STERLING Telecom & Const Inc Contractor
Other Seattle Neighborhood
Project Overview
Project Details
Value
$70,000
Type
Commercial Construction
Issued
December 17, 2025
Location
Other Seattle
Contractor Information
Location & Map
Project Description
Verizon EXPO DAS Node 10 Construct new light pole with minor telecommunications facility (Verizon), per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
STERLTC884C9
Housing category
Commercial Add/Alt
Review level
Full +
Primary use
Commercial
Parcel
DV0335960
Related land-use permit
3042816-LU
Review cycles
3
Plan review days
97
Days in corrections
79
Expires
June 17, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0